scanlobi.blogg.se

Rocky mountain power idaho falls
Rocky mountain power idaho falls













rocky mountain power idaho falls

He graduated from Idaho Falls High School in 1990. Steve was born November 12, 1972, in Idaho Falls, Idaho, to Paul Waggoner and Doris McGary. Paine was instrumental in the development of the utilities Bulb Turbine and Gem State hydroelectric projects along with countless other resources that our community enjoys today that enable us to provide some of the lowest cost, highest reliability electric service in the nation.Steven "Spanky" Neal Waggoner, 49, of Idaho Falls, passed away on August 2, 2022, at Idaho Falls Community Hospital, surrounded by his family. The substation is named in honor of the utility’s former chief engineer, Jeff Paine. The contractor, Bodec, began work on the substation in February 2021. The future Paine Substation, will be located to the northwest end the utility’s service area, is under construction for the cost of roughly $2,500,000. In near future, Rocky Mountain Power will tap from the line to go to its Rigby Substation to the north and its Bonneville Substation to the west. The project will involve the installation of approximately 14 miles of steel structures and accompanying high voltage conductor and lower voltage under build circuits including communication lines. The total cost of the line including property, right-of-way acquisition construction and materials will be roughly $14,500,000. at the start of 2021 to begin construction on the power line portion of the project. Idaho Falls Power contracted with Summit Line Construction Inc. The utilities entered into a Procurement and Construction Agreement wherein ownership and construction costs would be shared by each utility relative to their ownership/usage in the project. In 2017, IFP partnered with PacifiCorp (Rocky Mountain Power), as both utilities saw that this transmission line would benefit both utilities to better serve growth within the City and also outside of the City for Rocky Mountain Power customers in the area. The project faced some legal challenges from concerned stakeholders in the region in 2011, but IFP continued to work on purchasing easements and rights-of-way from landowners. The utility also began negotiations to acquire property, rights-of-way, and easements to construct the transmission line. Consultants in coordination with stakeholders began discussions on potential sites and routing options. In 2008, IFP hired an engineering consultant and began public outreach to create a design for the future 161kV transmission line, which is currently called the Sugarmill to Paine 161kV Transmission line. The original design was for this to be a larger project that would also serve the northern portion of the city as well. Idaho Falls Power ( IFP) first built a 161kV transmission line, located on the southern portion of the city connecting the Westside Substation to the Sugarmill Substation, in the 1980s. Sugarmill to Paine 161kV Transmission Line History The transmission line and the Paine substation are expected to be completed in October 2021. Highway 20 near 25th then travel to the west and across the Snake River to the future Paine Substation, which is also under construction. Idaho Falls Power, along with PacifiCorp, is constructing a 14-mile 161kV Transmission line connecting the Sugarmill Substation along Hitt Road and extend across Lincoln and Yellowstone. Sugarmill to Paine 161kV Transmission LineĬonstruction is currently underway to improve power transmission capacity and provide needed reliability investments to the power system serving the northern portion of the City of Idaho Falls and also benefitting all of eastern Idaho’s transmission grid.















Rocky mountain power idaho falls